Installation / Preparation for commissioning
22
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Deutschland
Telefon +49 711 3409-0, Telefax +49 711 3409-133, E-Mail: [email protected]
English
In particular, sources of conducted interference such as frequency-
controlled drives (circuit feedback) have a negative effect on the function of
the measuring system.
The 24 V power supplies must comply with SELV/PELV.
The shielding effect of cables must also be guaranteed after
installation (bending radius!) and after changing connectors. If in
doubt, use a more flexible cable with a higher current carrying
capacity.
For the drive/motor cabling, use a 5-core cable on which the PE
conductor is separate from the N-conductor (TN network). This will
largely prevent equipotential bonding currents and the development of
interference.
Shielded, stranded data cable must be used to make the system highly
resistant to electromagnetic interference. Where possible, the shield
should be connected to the protective earth at both ends and with
good conductivity using large screen clamps. Only if the machine earth
is subjected to heavy interference in comparison with the control
cabinet earth should the shield only be earthed at one end in the
control cabinet.
Equipotential bonding measures must be provided for the whole of the
plant’s processing chain.
Power and signal cables should be laid separately.
Comply with the manufacturer’s instructions when installing converters
and shielding the power cables between the frequency converter and
motor.
The energy supply should be adequately dimensioned.
The measuring system should be separated or segregated from
potential interfering transmitters.
Use of filters should be envisaged.
Internal and external protection against lightning should be considered.
The plant installer must adapt the cable routing to local conditions.
Compliance with the relevant standards and directives is essential to
guarantee safe, interference-free operation!
In particular, compliance with the applicable EMC Directive and shielding /
earthing guidelines should be guaranteed!